Question1: Who is responsible for the application of Principle 8, Demonstrate Control?

Question2: Which plain defined by DSDM, has a planning horizon that includes the end of a project?

Question3: Which responsibility relates to the role of the Business Ambassador?

Question4: Which practice provides an interactive environment in which all key players can contribute to the outcome?

Question5: Which purpose relates to the Consolidation in a structured Timebox?

Question6: When initially creating MoSCoW priorities, what is the primary focus?

Question7: When is a Timebox Plan updated?

Question8: Which competence is NOT required within the Solution Development team?

Question9: How is Quality ensured during Evolutionary Development?

Question10: During what phase should a baseline of the Evolving Solution be put into operational use?

Question11: How is contingency typically managed in a DSDM project?

Question12: Which statement about change is correct for DSDM?

Question13: When using the Iterative Development technique, which of the following should each cycle include?
1. Though
2. Action
3. Control
4. Conversation

Question14: What role, ideally, should be independent of the outcome to be achieved in a Facilitated Wordshop?

Question15: How does DSDM differ from most other Agile approaches?

Question16: Identify the missing word in the following sentence.
The Business Sponsor is known as the project [?] because they are committed to the solution and the delivery approach.

Question17: Identify the missing words in the following sentence.
Principles 1 -Focus on the Business Need suggests that every decision taken during a project should be [?] - to deliver what the business needs to be delivered.

Question18: Which statement applies to the DSDM process?

Question19: Which phase in the DSDM process aims to understand the scope of work and, in broad terms, how it will carried out, by whom, when and where?

Question20: During what DSDM phase is it established how quality to be assured?

Question21: How are the business roles critical to the success of a DSDM project?

Question22: How should DSDM team measure progress?